Notes:
8/25/2020 3:50:52 PM
Need to review/confirm quantities with engineer - the quantities on permit currently were provided by the contractor. Appears need to add storm sewer private. Need to add street degradation once we determine cut size from patching permit. TCP submitted under DEV for review - need to confirm who will be installing TCP. Need materials submittal.
5/25/2022 10:37:32 AM
The front counter added Timberwolf to this permit; per Eddie M. Hall Irwin’s plan is to use Timberwolf to finish up any remaining utility items not completed by BEC and to see the project through into initial acceptance to include preliminary and initial acceptance items. Hall Irwin is also planning on using them to complete the remaining curb gutter and sidewalk not completed by JAR Concrete. Let me know if I need to hold off on inspecting any requests for both utilities and concrete.
9/29/2022 12:24:21 PM
BEC is no longer in business but were the original contractor on this development for utilities.