PLEASE ASSIGN TO EDDIE MARTINEZ.
KDPL (Westminster transmission line) being constructed but they need to build crossings (sleeves) for the eventual utilities that will be coming once Trailstone is approved. This permit is only for those crossings/red highlighted areas on attached sheets. No traffic control plans needed per Jake. Only sales/use tax to be collected on this permit; any quantities will be reflected on the eventual DEV permit.
7/27/2022 11:17:05 AM
We have the permit application, we just need the job value to collect sales and use tax.
7/29/2022 11:47:41 AM
Permit has been issued. We will collect sales and use tax on DEV permit when it's issued per Jake.