| Heading | 07/19/2024 | UNDERGROUND PLUMB | Pete Henz | APPROVED | | |
|
| Heading | 07/24/2024 | ROUGH ELECTRIC | Mike McDonald | DENIED | | 7/24/2024 8:38:10 AM
Unit not ready at time of inspection.
p-rings missing along west wall
grounding incomplete
|
|
| Heading | 07/24/2024 | ROUGH FRAMING | Daniel Amador | DENIED | | 7/24/2024 8:44:39 AM
All MEP's need to pass prior to rough framing inspection.
|
|
| Heading | 07/26/2024 | ROUGH ELECTRIC | Mike McDonald | PARTIAL INSPECTION | | 7/26/2024 9:44:05 AM
Demising wall rough approved
|
|
| Heading | 07/26/2024 | ROUGH PLUMBING | Daniel Amador | APPROVED | | |
|
| Heading | 07/26/2024 | ROUGH ELECTRIC | Monique Ramirez | CANCELLED | | |
|
| Heading | 07/29/2024 | DRYWALL | Daniel Amador | PARTIAL INSPECTION | | 7/29/2024 9:50:47 AM
Drywall on demising wall from the east adjacent unit side only.
|
|
| Heading | 07/29/2024 | ROUGH FRAMING | Daniel Amador | PARTIAL INSPECTION | | 7/29/2024 9:48:55 AM
Demising wall only, not ready for entire rough frame inspection at this time.
|
|
| Heading | 08/02/2024 | ROUGH ELECTRIC | Brad Umbarger | APPROVED | | 8/2/2024 1:45:26 PM
Remainder of walls.
|
|
| Heading | 08/06/2024 | ROUGH FRAMING | Daniel Amador | DENIED | | 8/6/2024 8:58:30 AM
Not ready for framing inspection. Workers removing steel studs and working on backing throughout project at time of inspection.
|
|
| Heading | 08/07/2024 | ROUGH FRAMING | Daniel Amador | APPROVED | | |
|
| Heading | 08/09/2024 | INSULATION | Pete Henz | APPROVED | | |
|
| Heading | 08/16/2024 | DRYWALL | Daniel Amador | APPROVED | 1037 | 8/15/2024 1:45:07 PM
8/15/2024 1:45 PM SEIBEL CONSTRUCTION
Tommy is out. Please call Cole if needed 303-916-1886 .Thanks!
Contact Name: SEIBEL CONSTRUCTION
Site Address: 18148 W 92ND LN 200
Phone: 3039161886
e-Mail: [email protected]
|
|
| Heading | 08/22/2024 | ELEC ABOVE CEILING | Mike McDonald | APPROVED W/COND | am inspection request | 8/22/2024 10:17:42 AM
Verify at final: J-B's closed and access panels for all elec. boxes plastic bushings on data conduit by panel
|
|
| Heading | 08/22/2024 | ROUGH FRAMING | Daniel Amador | PARTIAL INSPECTION | pm inspection request | 8/22/2024 1:48:28 PM
Grid ceiling only.
|
|
| Heading | 08/22/2024 | ROUGH HVAC | Daniel Amador | APPROVED | am inspection request | |
|
| Heading | 08/27/2024 | DRYWALL | Daniel Amador | APPROVED | | 8/27/2024 9:07:55 AM
Hard lids
|
|
| Heading | 09/13/2024 | ELEC SERVICE/CL | Mike McDonald | APPROVED | eTRAKiT Inspection Request | 9/12/2024 1:35:06 PM
9/12/2024 1:35 PM COLORADO ELECTRICAL & SMART INTEGRATION
Call Mark once 30 minutes out.
720-447-0354
Contact Name: COLORADO ELECTRICAL & SMART INTEGRATION
Site Address: 18148 W 92ND LN 200
Phone: 7203180929
e-Mail: [email protected]
|
|
| Heading | 09/23/2024 | FINAL ELECTRICAL** | Mike McDonald | DENIED | | 9/23/2024 9:58:45 AM
All receptacles correct polarity, west wall in front room
Have all lighting installed and all devices; hand dryer, blanks for low volt, water cooler, power to A/V rack, no power to RTU service receptacle
missing exhaust fan cover.
panel schedule and required warning labels arc fault current and arc flash on all equipment
missing exit signs at south doors x 2
have print match install for RTU (print calls for #6) #8 installed
|
|
| Heading | 09/23/2024 | FINAL HVAC** | Pete Henz | DENIED | | 9/23/2024 8:56:05 AM
1. Return air locations not matching layout. Refer to city approved plans for locations.
2. All return air grills to be installed at final HVAC inspection.
|
|
| Heading | 09/24/2024 | FINAL ELECTRICAL** | Mike McDonald | APPROVED | | |
|
| Heading | 09/24/2024 | FINAL HVAC** | Daniel Amador | DENIED | | 9/24/2024 9:11:20 AM
Exhaust termination not complete and need balance report uploaded.
|
|
| Heading | 09/24/2024 | FINAL PLUMBING** | Daniel Amador | APPROVED | | |
|
| Heading | 09/25/2024 | FINAL HVAC** | Daniel Amador | APPROVED | | |
|
| Heading | 09/26/2024 | CO/TCO | Monique Ramirez | ACCEPTED | | |
|
| Heading | 09/26/2024 | FINAL STRUCTURAL** | Daniel Amador | DENIED | ok to apply for TCO, stock & training | 9/26/2024 10:20:59 AM
Both counter tops not installed. Everything else ok.
ok to apply for TCO, stock & training only.
|
|
| Heading | 12/06/2024 | CO/TCO | Monique Ramirez | ACCEPTED | | 12/6/2024 8:40:47 AM
Waiting on final inspection to be approved.
|
|
| Heading | 12/06/2024 | FINAL STRUCTURAL** | Daniel Amador | APPROVED | | |
|
| Heading | | STRUCTURAL SHEATHING | Daniel Amador | | | |
|