Permit No. COMM24-00073 Permit Type   COMMERCIAL Site Address   18148 W 92ND LN 200
ARVADA, CO 80007-
Applied   05/06/2024 Applicant   Ryan Brown
Approved   07/18/2024 Owner   Candelas Point, LLC
Issued   07/18/2024 Contractor   SEIBEL CONSTRUCTION
Parent Permit No.   Description   1,600 SF Tenant Finish
  Notes   Studio Pilates
 
Date of Inspection Inspection Type Inspector Result Remarks Notes

Heading 07/19/2024UNDERGROUND PLUMBPete HenzAPPROVED

Heading 07/24/2024ROUGH ELECTRICMike McDonaldDENIED7/24/2024 8:38:10 AM Unit not ready at time of inspection. p-rings missing along west wall grounding incomplete

Heading 07/24/2024ROUGH FRAMINGDaniel AmadorDENIED7/24/2024 8:44:39 AM All MEP's need to pass prior to rough framing inspection.

Heading 07/26/2024ROUGH ELECTRICMike McDonaldPARTIAL INSPECTION7/26/2024 9:44:05 AM Demising wall rough approved

Heading 07/26/2024ROUGH PLUMBINGDaniel AmadorAPPROVED

Heading 07/26/2024ROUGH ELECTRICMonique RamirezCANCELLED

Heading 07/29/2024DRYWALLDaniel AmadorPARTIAL INSPECTION7/29/2024 9:50:47 AM Drywall on demising wall from the east adjacent unit side only.

Heading 07/29/2024ROUGH FRAMINGDaniel AmadorPARTIAL INSPECTION7/29/2024 9:48:55 AM Demising wall only, not ready for entire rough frame inspection at this time.

Heading 08/02/2024ROUGH ELECTRICBrad UmbargerAPPROVED8/2/2024 1:45:26 PM Remainder of walls.

Heading 08/06/2024ROUGH FRAMINGDaniel AmadorDENIED8/6/2024 8:58:30 AM Not ready for framing inspection. Workers removing steel studs and working on backing throughout project at time of inspection.

Heading 08/07/2024ROUGH FRAMINGDaniel AmadorAPPROVED

Heading 08/09/2024INSULATIONPete HenzAPPROVED

Heading 08/16/2024DRYWALLDaniel AmadorAPPROVED10378/15/2024 1:45:07 PM 8/15/2024 1:45 PM SEIBEL CONSTRUCTION Tommy is out. Please call Cole if needed 303-916-1886 .Thanks! Contact Name: SEIBEL CONSTRUCTION Site Address: 18148 W 92ND LN 200 Phone: 3039161886 e-Mail: [email protected]

Heading 08/22/2024ELEC ABOVE CEILINGMike McDonaldAPPROVED W/CONDam inspection request8/22/2024 10:17:42 AM Verify at final: J-B's closed and access panels for all elec. boxes plastic bushings on data conduit by panel

Heading 08/22/2024ROUGH FRAMINGDaniel AmadorPARTIAL INSPECTIONpm inspection request8/22/2024 1:48:28 PM Grid ceiling only.

Heading 08/22/2024ROUGH HVACDaniel AmadorAPPROVEDam inspection request

Heading 08/27/2024DRYWALLDaniel AmadorAPPROVED8/27/2024 9:07:55 AM Hard lids

Heading 09/13/2024ELEC SERVICE/CLMike McDonaldAPPROVEDeTRAKiT Inspection Request9/12/2024 1:35:06 PM 9/12/2024 1:35 PM COLORADO ELECTRICAL & SMART INTEGRATION Call Mark once 30 minutes out. 720-447-0354 Contact Name: COLORADO ELECTRICAL & SMART INTEGRATION Site Address: 18148 W 92ND LN 200 Phone: 7203180929 e-Mail: [email protected]

Heading 09/23/2024FINAL ELECTRICAL**Mike McDonaldDENIED9/23/2024 9:58:45 AM All receptacles correct polarity, west wall in front room Have all lighting installed and all devices; hand dryer, blanks for low volt, water cooler, power to A/V rack, no power to RTU service receptacle missing exhaust fan cover. panel schedule and required warning labels arc fault current and arc flash on all equipment missing exit signs at south doors x 2 have print match install for RTU (print calls for #6) #8 installed

Heading 09/23/2024FINAL HVAC**Pete HenzDENIED9/23/2024 8:56:05 AM 1. Return air locations not matching layout. Refer to city approved plans for locations. 2. All return air grills to be installed at final HVAC inspection.

Heading 09/24/2024FINAL ELECTRICAL**Mike McDonaldAPPROVED

Heading 09/24/2024FINAL HVAC**Daniel AmadorDENIED9/24/2024 9:11:20 AM Exhaust termination not complete and need balance report uploaded.

Heading 09/24/2024FINAL PLUMBING**Daniel AmadorAPPROVED

Heading 09/25/2024FINAL HVAC**Daniel AmadorAPPROVED

Heading 09/26/2024CO/TCOMonique RamirezACCEPTED

Heading 09/26/2024FINAL STRUCTURAL**Daniel AmadorDENIEDok to apply for TCO, stock & training9/26/2024 10:20:59 AM Both counter tops not installed. Everything else ok. ok to apply for TCO, stock & training only.

Heading 12/06/2024CO/TCOMonique RamirezACCEPTED12/6/2024 8:40:47 AM Waiting on final inspection to be approved.

Heading 12/06/2024FINAL STRUCTURAL**Daniel AmadorAPPROVED