Notes:
8/8/2019 4:28:40 PM
Need contractor to finish filling out paperwork, traffic control and job value
8/16/2019 1:49:47 PM
Traffic control received
8/22/2019 3:16:12 PM
~Signed Permit by contractor doing work (not general) - Received
~Job value - Received
~Traffic control - Received
~Sub Contractor sign on for Traffic - needed *****
9/26/2019 9:02:52 AM
We are still missing Material Submittals. Please email with signed and stamped cover letter. Okay to approve permit w/o submittals to get work completed prior to paving of 72nd. Also, still need traffic control sub contractor sign on form.
9/26/2019 4:55:12 PM
Traffic control to be set up by Colorado Civil Infrastructure
11/4/2019 3:59:39 PM
Per Kirk DeWitt (developer) they are working on finding a new contractor to replace CCI; did not work out. Provided email with permit fees CCI has paid as of today. Advised needs to let us know if all the work under the wet utility permit has been completed by CCI or if the other contractor will be taking over this permit. If other contractor taking over the permit will need the traffic control sub contractor sign on form completed.
12/17/2019 2:49:40 PM
Email from Emiley Y. - CCI no longer working on project; have submitted new permit application from Blanco for wet utilities. Project will have new contractors for utilities, concrete and signing/striping.
12/17/2019 2:51:16 PM
Email to Juan at Blanco - need to confirm traffic control contractor and if using previously approved plan. Need to pick up spec book.
9/13/2023 10:51:19 AM
9/13/23 - City issued final acceptance for this project.